Usetutoringspotscode to get 8% OFF on your first order!

  • time icon24/7 online - support@tutoringspots.com
  • phone icon1-316-444-1378 or 44-141-628-6690
  • login iconLogin

The following lists of jobs in a critical department includes estimates of their required times:

The following lists of jobs in a critical department includes estimates of their required times:

JOB Required time (days) Days to delivery promise Slack
A 8 12 4
B 3 9 6
C 7 8 1
D 1 11 10
E 10 -10 –
F 6 10 4
G 5 -8 –
H 4 6 2

A. Use the shortest operation time rule to schedule these jobs. What is the schedule? What is the mean flow time?

B. Assume the schedule in “a” is not acceptable for management. Jobs E and G must be done first, for obvious reasons as they are already late. Reschedule and do the best you can while scheduling jobs E and G first and second, respectively. What is the new schedule? what is the new mean flow?

You can leave a response, or trackback from your own site.

Leave a Reply

Powered by WordPress | Designed by: Premium WordPress Themes | Thanks to Themes Gallery, Bromoney and Wordpress Themes