Usetutoringspotscode to get 8% OFF on your first order!

  • time icon24/7 online - support@tutoringspots.com
  • phone icon1-316-444-1378 or 44-141-628-6690
  • login iconLogin

OSHA

OSHA

Order Description

It is important to stay current on issues related to safety. This week, visit the OSHA website (www.osha.gov) Locate a news release on an OSHA activity. Provide a summary of the news release and discuss what OSHA is trying to do, the effect on the workers and the effect on the employers. Try to find a unique story that has not already been discussed in this forum.

You can leave a response, or trackback from your own site.

Leave a Reply

OSHA

OSHA
Assignment 2
The M&M Textile Mill was inspected by OSHA and found to be in violation of a number of safety
regulations. The OSHA inspectors orders the mill to alter some existing machinery to make it
safer(safer guards etc.); purchase some new machinery to replace older, dangerous machinery; and
relocate some machinery to make safer passages and unobstructed entrances and exits. OSHA gives
the mill 40 weeks to make the changes; if the changes were not made by then, the mill would be
fined $300,000.
After consulting with members of the engineering staff, the director compiled a list of activities
associated with the project. The mill determined the activities in a CPM/PERT network that would
have to be completed and then estimated the indicated activity times, as shown in the following
table.
Activity Description Immediate
predecessor
Time estimates
a b m
Crashed
Cost ($)
Normal
cost ($)
Crashed
Activity
time
A Order new
machinery
– 4 6 8 1900 1000 4
B Plan new physical
layout
– 6 8 16 1800 1000 7
C Select contractors A,B 2 4 6 2700 1500 2
D Receive
equipment
C 8 10 24 3200 2000 8
E Receive designs C 7 10 13 8000 5000 7
F Make plant
alterations
E 4 6 8 4100 3000 4
G Make changes in
existing machinery
C 4 6 20 10250 8000 5
H Install new
machinery
D,F,G 4 6 8 6400 5000 4
I Relocate new
machinery
D,F 4 6 14 12400 10000 4
J Train system
operators
H 3 4 5 4400 4000 3
K Conduct safety
operations
I,J 2 4 6 5500 5000 3
Managerial report
Develop a report that presents the activity schedule and expected project completion time for the
M&M Textile Mill’s safety regulation project. Include project network diagram.
Also provide details on the following issues
1. According to OSHA order, can this completion time be achieve? Include probability
information in your discussion. What recommendations do you have if the 40-week
completion is required?
2. Suppose that management request that activity times be shortened to provide and 80%
chance of meeting the 40-week completion time. Then, how much should the expected
project completion time be shortened to achieve the goal of an 80% chance of completion
within 40 weeks?
3. Using the expected activity times as the normal times and the following crashing
information, determine activity crashing decisions and revised activity schedule for the
project.

Assignment 2
The M&M Textile Mill was inspected by OSHA and found to be in violation of a number of safety
regulations. The OSHA inspectors orders the mill to alter some existing machinery to make it
safer(safer guards etc.); purchase some new machinery to replace older, dangerous machinery; and
relocate some machinery to make safer passages and unobstructed entrances and exits. OSHA gives
the mill 40 weeks to make the changes; if the changes were not made by then, the mill would be
fined $300,000.
After consulting with members of the engineering staff, the director compiled a list of activities
associated with the project. The mill determined the activities in a CPM/PERT network that would
have to be completed and then estimated the indicated activity times, as shown in the following
table.
Activity Description Immediate
predecessor
Time estimates
a b m
Crashed
Cost ($)
Normal
cost ($)
Crashed
Activity
time
A Order new
machinery
– 4 6 8 1900 1000 4
B Plan new physical
layout
– 6 8 16 1800 1000 7
C Select contractors A,B 2 4 6 2700 1500 2
D Receive
equipment
C 8 10 24 3200 2000 8
E Receive designs C 7 10 13 8000 5000 7
F Make plant
alterations
E 4 6 8 4100 3000 4
G Make changes in
existing machinery
C 4 6 20 10250 8000 5
H Install new
machinery
D,F,G 4 6 8 6400 5000 4
I Relocate new
machinery
D,F 4 6 14 12400 10000 4
J Train system
operators
H 3 4 5 4400 4000 3
K Conduct safety
operations
I,J 2 4 6 5500 5000 3
Managerial report
Develop a report that presents the activity schedule and expected project completion time for the
M&M Textile Mill’s safety regulation project. Include project network diagram.
Also provide details on the following issues
1. According to OSHA order, can this completion time be achieve? Include probability
information in your discussion. What recommendations do you have if the 40-week
completion is required?
2. Suppose that management request that activity times be shortened to provide and 80%
chance of meeting the 40-week completion time. Then, how much should the expected
project completion time be shortened to achieve the goal of an 80% chance of completion
within 40 weeks?
3. Using the expected activity times as the normal times and the following crashing
information, determine activity crashing decisions and revised activity schedule for the
project.

Responses are currently closed, but you can trackback from your own site.

Comments are closed.

OSHA

OSHA
Assignment 2
The M&M Textile Mill was inspected by OSHA and found to be in violation of a number of safety
regulations. The OSHA inspectors orders the mill to alter some existing machinery to make it
safer(safer guards etc.); purchase some new machinery to replace older, dangerous machinery; and
relocate some machinery to make safer passages and unobstructed entrances and exits. OSHA gives
the mill 40 weeks to make the changes; if the changes were not made by then, the mill would be
fined $300,000.
After consulting with members of the engineering staff, the director compiled a list of activities
associated with the project. The mill determined the activities in a CPM/PERT network that would
have to be completed and then estimated the indicated activity times, as shown in the following
table.
Activity Description Immediate
predecessor
Time estimates
a b m
Crashed
Cost ($)
Normal
cost ($)
Crashed
Activity
time
A Order new
machinery
– 4 6 8 1900 1000 4
B Plan new physical
layout
– 6 8 16 1800 1000 7
C Select contractors A,B 2 4 6 2700 1500 2
D Receive
equipment
C 8 10 24 3200 2000 8
E Receive designs C 7 10 13 8000 5000 7
F Make plant
alterations
E 4 6 8 4100 3000 4
G Make changes in
existing machinery
C 4 6 20 10250 8000 5
H Install new
machinery
D,F,G 4 6 8 6400 5000 4
I Relocate new
machinery
D,F 4 6 14 12400 10000 4
J Train system
operators
H 3 4 5 4400 4000 3
K Conduct safety
operations
I,J 2 4 6 5500 5000 3
Managerial report
Develop a report that presents the activity schedule and expected project completion time for the
M&M Textile Mill’s safety regulation project. Include project network diagram.
Also provide details on the following issues
1. According to OSHA order, can this completion time be achieve? Include probability
information in your discussion. What recommendations do you have if the 40-week
completion is required?
2. Suppose that management request that activity times be shortened to provide and 80%
chance of meeting the 40-week completion time. Then, how much should the expected
project completion time be shortened to achieve the goal of an 80% chance of completion
within 40 weeks?
3. Using the expected activity times as the normal times and the following crashing
information, determine activity crashing decisions and revised activity schedule for the
project.

Assignment 2
The M&M Textile Mill was inspected by OSHA and found to be in violation of a number of safety
regulations. The OSHA inspectors orders the mill to alter some existing machinery to make it
safer(safer guards etc.); purchase some new machinery to replace older, dangerous machinery; and
relocate some machinery to make safer passages and unobstructed entrances and exits. OSHA gives
the mill 40 weeks to make the changes; if the changes were not made by then, the mill would be
fined $300,000.
After consulting with members of the engineering staff, the director compiled a list of activities
associated with the project. The mill determined the activities in a CPM/PERT network that would
have to be completed and then estimated the indicated activity times, as shown in the following
table.
Activity Description Immediate
predecessor
Time estimates
a b m
Crashed
Cost ($)
Normal
cost ($)
Crashed
Activity
time
A Order new
machinery
– 4 6 8 1900 1000 4
B Plan new physical
layout
– 6 8 16 1800 1000 7
C Select contractors A,B 2 4 6 2700 1500 2
D Receive
equipment
C 8 10 24 3200 2000 8
E Receive designs C 7 10 13 8000 5000 7
F Make plant
alterations
E 4 6 8 4100 3000 4
G Make changes in
existing machinery
C 4 6 20 10250 8000 5
H Install new
machinery
D,F,G 4 6 8 6400 5000 4
I Relocate new
machinery
D,F 4 6 14 12400 10000 4
J Train system
operators
H 3 4 5 4400 4000 3
K Conduct safety
operations
I,J 2 4 6 5500 5000 3
Managerial report
Develop a report that presents the activity schedule and expected project completion time for the
M&M Textile Mill’s safety regulation project. Include project network diagram.
Also provide details on the following issues
1. According to OSHA order, can this completion time be achieve? Include probability
information in your discussion. What recommendations do you have if the 40-week
completion is required?
2. Suppose that management request that activity times be shortened to provide and 80%
chance of meeting the 40-week completion time. Then, how much should the expected
project completion time be shortened to achieve the goal of an 80% chance of completion
within 40 weeks?
3. Using the expected activity times as the normal times and the following crashing
information, determine activity crashing decisions and revised activity schedule for the
project.

Responses are currently closed, but you can trackback from your own site.

Comments are closed.

Powered by WordPress | Designed by: Premium WordPress Themes | Thanks to Themes Gallery, Bromoney and Wordpress Themes