Develop a drum schedule (pipeline) for multiple projects by their priority and insert the capacity-constraint buffers (CCB) and drum (capacity) buffers as needed.
1.The capacity of the drum resource is 2 units.
2.The drum is resource B
3.The priority of the projects is project 1, project 2, then project 3.