this course is decision modeling and analysis. problem #7 is from chapter 3 (Linear and Programming) and the Memorandum format is from chapter 1
Decision modeling and analysis.
August 10th, 2017 admin
Leave a Reply
Decision Modeling and Analysis
January 13th, 2016 admin
Ajax is about to embark on a project involving the design, manufacture and introduction of a new microwave oven. The first three activities and the immediate predecessors are:
Activity Predecessor
A Prototype Design none
B Acquisition of Materials A
C Prototype Construction B
However, it has not yet been decided whether the prototype materials will be purchased from a vendor (taking two weeks) or produced in another Ajax division (four weeks). What are the implications of this regarding usage of any standard project scheduling technique