icon

Usetutoringspotscode to get 8% OFF on your first order!

Construction law

Construction law

All answers to be submitted using Australian laws and legislation
References to the following topics and cases
– Bellgrove v Eldridge [1954] 90 CLR 613 (defective works)
– Tabcorp Holdings LTD  v  Bowen Investments PTY LTD (defective works)
-GRAHAM EVANS PTY LTD v STENCRAFT PTY LTD – BC9907871 (construction Contract)
(Files have been attached)

Question 1

VP Investments Pty Ltd (VPI) engaged builder PL Pty Ltd (PL) under a standard form building contract to construct a 6-storey building to provide office space to carry out their business operations. The contract sum was $20,000,000.

The project went very smoothly and VPI was able to move into the facility on time. However over the first few months during summer, management at VPI were getting complaints from staff that the office spaces were too warm and uncomfortable.

VPI approached PL’s project manager Paul about this problem and he said the mechanical systems were all installed properly and there was no need to worry as it was getting towards the end of summer. VPI decided to get their services consultants to check the installation and found that the air handling units installed were not in accordance with the drawings or mechanical specification.
In fact not only were the units a different make, but they were slightly undersized from the capacity stated in the specification.

Paul had an independent engineer check the installation who advised that the installation complied with the relevant standards and codes, and in fact the client had too many people in the building which increased the heat load. This independent report together with the fact PL had been paid out their contract (minus retention) VPI could not get Paul to agree to fix the problem.

VPI decide to obtain advice on this matter and contact you.

Advise VPI what entitlements under contract may be available in respect to defective building works.
Question 2

Assume the situation in Question 1 occurred (the mechanical system was defective), and on inspection of the installation it was found the work was carried out by PL correctly and in accordance with the drawings and specification.

Consider the issues, and provide advice to VPI on their possible rights under contract and relevant legislation.
Question 3
Assume after investigation of the mechanical system by an independent engineer determined the design of the system carried out by an engineer engaged by VPI was inadequate, as was the materials and workmanship provided by PL.

Provide advice to VPI based on this scenario.
Question 4
If the defective work identified in Question 1 was carried out under a domestic building contract, what considerations would you have to take into account when providing advice to your client.
TO ORDER FOR THIS QUESTION OR A SIMILAR ONE, CLICK THE ORDER NOW BUTTON AND ON THE ORDER FORM, FILL ALL THE REQUIRED DETAILS THEN TRACE THE DISCOUNT CODE, TYPE IT ON THE DISCOUNT BOX AND CLICK ON ‘USE CODE’ TO EFFECT YOUR DISCOUNT. THANK YOU

You can leave a response, or trackback from your own site.

Leave a Reply

Construction Law

Construction Law

The writer must be a qualified writer in UK, since I’m studying in UK university.
This order consists of two separate coursework, one is titled as Construction Law and the other is Advanced Construction Law. Two files to be uploaded, each represents the questions and guidlines of each coursework.
OSCOLA referencing style should be strictly followed.
Writer must strictly adhere to the minimum word counts shown at the end of each question (plus 5 – 10%), regardless of number of pages. Completed work for each coursework should not be under any circumstances ONE word less than the mentioned word counts, which is as following for each coursework:
1- Section A 1,800 words
2- Section B 1,350 words
Writer must respect the deadline with no impact on work quality, and it is necessarily required to complete at first the Construction Law coursework (file no. 1), since in case any unexpected delay happens, this coursework deadline is earlier than the second one.
The writer may use whatever sources he or she feels are most appropriate, however, a list of essential sources is being prepared to be considered by the writer, and will be uploaded very shortly. This should not delay the writer to start working.
Writer must include a table of content and bibliography and to arrange it should adhere to the coursework guidelines stated at the beginning of each coursework file.
A plagiarism report is required.
All the above must be read in context with the coursework guidelines stated at the beginning of each coursework file.

The following guidelines should be strictly adhered to:

1. All propositions of law referred to in the legal problem question – see section A of the assignment below – should be supported by an appropriate reference to a case or statute or, in the case of a reference to a standard form of building contract such as the JCT Design and Build Contract 2011 Edition, by an appropriate reference to the relevant contract.

2. The minimum word limits for each component of the assignment appear at the end of the relevant section of the assignment. These limits should be adhered to.

3. Footnotes/endnotes should be included in the essay. A bibliography should appear at the end of the essay. The bibliography should contain all relevant material consulted by the student, whether referred to in footnotes or not and material in the bibliography should be arranged under the following headings, where applicable:

Legislation
Case Law
Internet resources
Other resources

Words in footnotes and bibliography should not be included when taking into account the essay word count.

4. Footnotes/endnotes must be used for referencing and further reading only and should contain as little text as possible.

Coursework Assignment

Section A
Legal Problem

After spending nearly a decade renovating maisonettes and terraced houses and undertaking other basic redevelopment schemes a property developer – Primitive Projects LLP (‘Primitive’) – decides to go to the next level by becoming involved in the development of a mixed residential and retail development at a town centre location in Leicester. Primitive engages a firm of contractors that it has used in the past on its smaller-scale projects – Facile Fabrications Limited (‘Facile’). Primitive is not aware that whenever, in the past, Facile has been engaged to undertake larger or more complex projects it has botched them. Unaware of Facile’s chequered history, then, Primitive engages Facile on the basis of the JCT Design and Build Contract 2011 Edition (unamended).

The Leicester project gets off to a good start. Workable designs are produced and, overall, the contract documentation appears quite sound. All the required approvals, permissions and certifications are speedily obtained in accordance with building regulations and planning laws and construction work gets underway on the commencement date scheduled in the contract.

A major national supermarket chain – MetroMart plc (‘MetroMart’) – expresses an interest in opening a local town centre store in Primitive’s completed development because they are scaling down their involvement in out-of-town superstores and selling off sites previously earmarked for major development. After a month or two of ‘toing and froing’ between the lawyers Primitive enters into a pre-letting agreement committing MetroMart to a ten year lease of the largest of the four retail units at street level of the development. Under the pre-letting agreement MetroMart secures wide-ranging powers of supervision and approval of the evolving construction works and key aspects of the internal fitting-out of the large unit pre-let to MetroMart.

A week after the commencement date of the pre-letting agreement MetroMart sends its architect to the site for a spot-check only to discover that the work on the MetroMart retail space is not taking shape in a way that is even remotely in accordance with what was planned or contracted-for.

For instance, the architect describes the finished floor levels as ‘wonky’. Some parts of the floor are a full 200-300mm higher than other parts and seem to take the form of large, unwieldy ‘shapes’ – squares and rectangles. “Why can’t they lay a level floor?” the architect exclaims.

“And what’s with all these ‘shapes’? It’s not a children’s play area – customers are going to trip and fall; and the shelving and refrigeration units won’t have a level surface to sit on!”

But that’s not the only problem discovered. The architect also points out that inferior and/or inappropriate building materials are being used – for instance cheap lino in the back shop areas instead of hard-wearing floor tiling. None of this conforms to the drawings or specifications in the contract documents. Also low quality windows and entrance doors have been installed, with the doors appearing to be loose-fitting and jamming on opening and closing.

The architects for both MetroMart and Facile have no difficulty agreeing that decisive action is needed to address Facile’s obvious departures from the approved designs and the separate, but related, issue of the use of inferior or inappropriate materials and obviously shoddy standards of work.

Question (A)

In answering this part of the question students should initially assume that the parties most closely connected with the project take the view that existing contractual mechanisms will be robust and/or effective enough to provide a solution to the difficulties that have arisen to date.

Therefore, discuss and evaluate the options available to Primitive under the JCT Design and Build Contract 2011 Edition for requiring Facile to address and put right the issues identified by MetroMart’s architect. This should include applying relevant factual provisions to the key facts of the problem scenario and considering procedural steps needing to be taken.

Question (B)

In answering this part of the question students should assume that the issues identified by MetroMart’s architect are too fundamental to admit of a straightforward resolution by way of the standard contractual mechanisms available under the JCT Design and Build Contract 2011 Edition. It should therefore be assumed that a resolution can be pursued only by way of the remedies available under the general law governing breach of contract.

In the context of offering legal and contractual advice to Primitive (and, by extension, to MetroMart), therefore, discuss and explain the feasibility of holding Facile to be in breach of contract under the general law of contract on account of the fundamental nature of Facile’s departures from the requirements of the contract entered into between Primitive and Facile.

In your answer, among other things, include consideration of: (A) the legal remedies available under the general law governing breach of contract, and (B) the applicability to this factual scenario of the common law doctrine of temporary disconformity, such as it is.

[Note that an answer that attempts to apply contractual provisions or legal principles to the specific facts of the problem scenario will attract a higher mark than an answer that does not.]

Word limit for Section A Legal Problem: minimum 1,800 words

Section B
Essay Topic

Critically evaluate the contractual position regarding variations of works in the JCT Standard Building Contract with Quantities 2011 edition, touching (among other things) upon how such variations impact on the employer’s payment obligation and on provisions of the contract allowing for extensions of time. Comment on how effective these contractual mechanisms are in practical terms. (For instance, you may choose either to make suggestions as to how these mechanisms might be improved upon – such as by drawing relevant comparisons with other types of standard form contracts (e.g. ICE, FIDIC etc.) – or show how the mechanisms as they currently stand are as effective as they possibly can be.)

Word limit for Section B Essay Topic: minimum 1,350 words

Responses are currently closed, but you can trackback from your own site.

Comments are closed.

Construction Law

Construction Law

The writer must be a qualified writer in UK, since I’m studying in UK university.
This order consists of two separate coursework, one is titled as Construction Law and the other is Advanced Construction Law. Two files to be uploaded, each represents the questions and guidlines of each coursework.
OSCOLA referencing style should be strictly followed.
Writer must strictly adhere to the minimum word counts shown at the end of each question (plus 5 – 10%), regardless of number of pages. Completed work for each coursework should not be under any circumstances ONE word less than the mentioned word counts, which is as following for each coursework:
1- Section A 1,800 words
2- Section B 1,350 words
Writer must respect the deadline with no impact on work quality, and it is necessarily required to complete at first the Construction Law coursework (file no. 1), since in case any unexpected delay happens, this coursework deadline is earlier than the second one.
The writer may use whatever sources he or she feels are most appropriate, however, a list of essential sources is being prepared to be considered by the writer, and will be uploaded very shortly. This should not delay the writer to start working.
Writer must include a table of content and bibliography and to arrange it should adhere to the coursework guidelines stated at the beginning of each coursework file.
A plagiarism report is required.
All the above must be read in context with the coursework guidelines stated at the beginning of each coursework file.

The following guidelines should be strictly adhered to:

1. All propositions of law referred to in the legal problem question – see section A of the assignment below – should be supported by an appropriate reference to a case or statute or, in the case of a reference to a standard form of building contract such as the JCT Design and Build Contract 2011 Edition, by an appropriate reference to the relevant contract.

2. The minimum word limits for each component of the assignment appear at the end of the relevant section of the assignment. These limits should be adhered to.

3. Footnotes/endnotes should be included in the essay. A bibliography should appear at the end of the essay. The bibliography should contain all relevant material consulted by the student, whether referred to in footnotes or not and material in the bibliography should be arranged under the following headings, where applicable:

Legislation
Case Law
Internet resources
Other resources

Words in footnotes and bibliography should not be included when taking into account the essay word count.

4. Footnotes/endnotes must be used for referencing and further reading only and should contain as little text as possible.

Coursework Assignment

Section A
Legal Problem

After spending nearly a decade renovating maisonettes and terraced houses and undertaking other basic redevelopment schemes a property developer – Primitive Projects LLP (‘Primitive’) – decides to go to the next level by becoming involved in the development of a mixed residential and retail development at a town centre location in Leicester. Primitive engages a firm of contractors that it has used in the past on its smaller-scale projects – Facile Fabrications Limited (‘Facile’). Primitive is not aware that whenever, in the past, Facile has been engaged to undertake larger or more complex projects it has botched them. Unaware of Facile’s chequered history, then, Primitive engages Facile on the basis of the JCT Design and Build Contract 2011 Edition (unamended).

The Leicester project gets off to a good start. Workable designs are produced and, overall, the contract documentation appears quite sound. All the required approvals, permissions and certifications are speedily obtained in accordance with building regulations and planning laws and construction work gets underway on the commencement date scheduled in the contract.

A major national supermarket chain – MetroMart plc (‘MetroMart’) – expresses an interest in opening a local town centre store in Primitive’s completed development because they are scaling down their involvement in out-of-town superstores and selling off sites previously earmarked for major development. After a month or two of ‘toing and froing’ between the lawyers Primitive enters into a pre-letting agreement committing MetroMart to a ten year lease of the largest of the four retail units at street level of the development. Under the pre-letting agreement MetroMart secures wide-ranging powers of supervision and approval of the evolving construction works and key aspects of the internal fitting-out of the large unit pre-let to MetroMart.

A week after the commencement date of the pre-letting agreement MetroMart sends its architect to the site for a spot-check only to discover that the work on the MetroMart retail space is not taking shape in a way that is even remotely in accordance with what was planned or contracted-for.

For instance, the architect describes the finished floor levels as ‘wonky’. Some parts of the floor are a full 200-300mm higher than other parts and seem to take the form of large, unwieldy ‘shapes’ – squares and rectangles. “Why can’t they lay a level floor?” the architect exclaims.

“And what’s with all these ‘shapes’? It’s not a children’s play area – customers are going to trip and fall; and the shelving and refrigeration units won’t have a level surface to sit on!”

But that’s not the only problem discovered. The architect also points out that inferior and/or inappropriate building materials are being used – for instance cheap lino in the back shop areas instead of hard-wearing floor tiling. None of this conforms to the drawings or specifications in the contract documents. Also low quality windows and entrance doors have been installed, with the doors appearing to be loose-fitting and jamming on opening and closing.

The architects for both MetroMart and Facile have no difficulty agreeing that decisive action is needed to address Facile’s obvious departures from the approved designs and the separate, but related, issue of the use of inferior or inappropriate materials and obviously shoddy standards of work.

Question (A)

In answering this part of the question students should initially assume that the parties most closely connected with the project take the view that existing contractual mechanisms will be robust and/or effective enough to provide a solution to the difficulties that have arisen to date.

Therefore, discuss and evaluate the options available to Primitive under the JCT Design and Build Contract 2011 Edition for requiring Facile to address and put right the issues identified by MetroMart’s architect. This should include applying relevant factual provisions to the key facts of the problem scenario and considering procedural steps needing to be taken.

Question (B)

In answering this part of the question students should assume that the issues identified by MetroMart’s architect are too fundamental to admit of a straightforward resolution by way of the standard contractual mechanisms available under the JCT Design and Build Contract 2011 Edition. It should therefore be assumed that a resolution can be pursued only by way of the remedies available under the general law governing breach of contract.

In the context of offering legal and contractual advice to Primitive (and, by extension, to MetroMart), therefore, discuss and explain the feasibility of holding Facile to be in breach of contract under the general law of contract on account of the fundamental nature of Facile’s departures from the requirements of the contract entered into between Primitive and Facile.

In your answer, among other things, include consideration of: (A) the legal remedies available under the general law governing breach of contract, and (B) the applicability to this factual scenario of the common law doctrine of temporary disconformity, such as it is.

[Note that an answer that attempts to apply contractual provisions or legal principles to the specific facts of the problem scenario will attract a higher mark than an answer that does not.]

Word limit for Section A Legal Problem: minimum 1,800 words

Section B
Essay Topic

Critically evaluate the contractual position regarding variations of works in the JCT Standard Building Contract with Quantities 2011 edition, touching (among other things) upon how such variations impact on the employer’s payment obligation and on provisions of the contract allowing for extensions of time. Comment on how effective these contractual mechanisms are in practical terms. (For instance, you may choose either to make suggestions as to how these mechanisms might be improved upon – such as by drawing relevant comparisons with other types of standard form contracts (e.g. ICE, FIDIC etc.) – or show how the mechanisms as they currently stand are as effective as they possibly can be.)

Word limit for Section B Essay Topic: minimum 1,350 words

Responses are currently closed, but you can trackback from your own site.

Comments are closed.

Powered by WordPress | Designed by: Premium WordPress Themes | Thanks to Themes Gallery, Bromoney and Wordpress Themes